Renovation: when you can just start and when you need a permit
The new Building Act no longer has a building notification. Which alterations and maintenance work need no permit, when you need one, how many days the office has to decide and what it costs.
Looking for how to "notify building work" (ohlášení stavby)? The new Building Act no longer has it. Either you can start the work straight away, or you need a permit. What matters is the type of work, not the size of the budget.

1. The basic rule
A project requires a permit, except for minor structures and changes in land use where the Act provides otherwise (Section 171 of Act No. 283/2021 Coll., the Building Act). Annex 1 to the Building Act lists which works count as a minor structure.
2. No permit needed
Under Annex 1(1)(e) of the Building Act, building alterations count as a minor structure if they meet all of these conditions:
- they do not affect load-bearing structures,
- they do not change the building's appearance or its use,
- they cannot adversely affect fire safety,
- the building is not a cultural monument.
Maintenance work also needs no permit if it cannot endanger people's health, fire safety, stability, the building's appearance, the environment or safety in use, unless the building is a cultural monument (Annex 1(1)(d) of Act No. 283/2021 Coll.).
3. When you need a permit
- You remove or alter a load-bearing wall.
- You change the building's appearance, such as the façade or the shape of the windows.
- You change the use, such as turning a flat into an office.
- The building is a cultural monument.
Some of this work is a simple structure, for example alterations for a change of use of part of a building that do not touch load-bearing structures or change its appearance (Annex 2(2)(d) of Act No. 283/2021 Coll.). Living in a block of flats? The consent of the building's owner or the owners' association (SVJ) is a separate matter outside the Building Act, so clarify it in advance.
4. Deadlines and fee
- The building office decides within 30 days of the start of proceedings for a simple structure, otherwise within 60 days (Section 196(1) of Act No. 283/2021 Coll.).
- In particularly complex cases it may extend the deadline by up to 30 days, in some cases by up to 60 days (Section 196(2) of Act No. 283/2021 Coll.).
- If the application has defects, the deadline starts again once they are fixed (Section 196(4) of Act No. 283/2021 Coll.).
- The administrative fee for the permit is CZK 5,000 for a simple structure and CZK 10,000 for other structures (Act No. 634/2004 Coll., fee schedule, item 18).
We help you draw up a list of works and of the documents you need, and we monitor the work against the contract. We do not choose the craftsman for you and are not liable for their work. Prices are given as an indicative price, not an expert valuation.